~ PROJECT ~ Craig Bridge Helena Montana Project Engineer: Martin Drivdahl Supplementary Information
This packet is to assist in initial determination of the process of re-erecting the Craig Bridge. The stats of the bridge are as follows.
Length: Measured with one piece steel contractor tape Section A, current western, Historic Center of Craig Bridge (136 feet, 6¼ inch) Approx. 22 Ton Section B, current center, Historic Sterling Ranch side of Craig Bridge (136 feet, 6 ¼ inch) Approx. 22 Ton Section C, current eastern, Historic Craig side of Craig Bridge (136 feet, 6 ¼ inch) Approx. 22 Ton Overall Length: Sections A,B,C, (409 feet 6 ¾ inch) Approx. 66 Ton
Width: Measured with one piece steel contractor tape Section A, current western, (18 feet, 1 ½ inch) Section B, current center, (18 feet, 1 ¼ inch) Section C, current eastern, (18 feet, 1 ½ inch)
Height: Measured with one piece steel contractor tape Section A, (23 feet) Section B, (23 feet) Section C, (23 feet)
These physical measurements were compared to ones done by the Department of Transportation prior to their removal from piers in 2005. The measurements are accurate to within ¼ inch
|